Before approving a change to an agreed remodeling scope, confirm what will change, what will remain, how the price and schedule will be affected, and which questions are still open. Keep those answers with the exact revision you are being asked to approve—not scattered across conversations, product photos and older drawings.
This remodel change order checklist is for decisions made after the original kitchen, bathroom or basement scope has been agreed. Use it to distinguish an idea you want explored from work you are ready to authorize.
Note This is a homeowner planning aid, not New England Home Pros’ contract or verified change-order procedure. Ask your project team which documents and approval process apply to your project.
Start with the agreed scope, then describe the difference
Identify the scope item, drawing, selection record or earlier approved revision that the proposed change would replace. Include its version or other identifying reference. If the current baseline is unclear, ask the team to reconcile it before reviewing another revision.
Describe the change as a comparison: what was agreed, what is proposed instead, and what stays untouched. Avoid descriptions such as “upgrade shower” or “revise basement layout” without identifying the affected work. Record whether the proposal adds work, removes work, substitutes a product or changes a location.
Also record why the change is being considered. A homeowner preference, an unavailable product and a newly discovered condition raise different questions. For a discovered condition, retain the relevant photos or field notes and ask the team to explain which proposed work addresses it and which work is optional.
Check the effects beyond the changed item
A revised selection or location needs to be reviewed in context. Ask what dimensions, connections, adjoining surfaces and retained features need another check. Keep this focused on the consequences of the proposed revision rather than reopening every selection in the project.
- Kitchen changes: If an appliance, sink or cabinet changes, ask whether the revision affects openings, clearances, utility connections or related countertop work.
- Bathroom changes: If a fixture, shower layout or surface changes, ask which adjacent preparation, connections and finishing work need to be included.
- Basement changes: If a partition or room layout changes, ask which door locations, lighting, outlets, access points or surrounding finishes need review.
Identify who will verify the affected details and what evidence will be retained. For model-specific fit and compatibility questions, use the kitchen and bathroom remodel product-selection checklist. Attach the revised selection reference to the change record so an earlier product approval is not mistaken for confirmation of the replacement.
Clarify pricing, credits and unresolved costs
Ask for the price effect of the complete revision, not just the replacement product. The description should make clear which added work, removed work and related adjustments are included. If pricing is not settled, label it unresolved rather than treating a blank field as no change.
- Added work: What materials, labor, preparation, removal and finishing are included in the proposed adjustment?
- Removed work and credits: What original work or materials will no longer be supplied, and how is that reflected in the adjustment?
- Existing commitments: Have affected materials already been ordered, delivered or installed? Ask whether cancellation, return, replacement or rework costs apply.
- Pricing status: Is the proposed adjustment confirmed or still subject to information? What remains to be priced, and how will that be resolved?
- Project total and payment: How would the revision change the agreed project total and any payment arrangements?
Ask what the change holds up or releases
A schedule note should explain more than “may cause delay.” Ask which purchasing, measurements, trade coordination or other decisions depend on the revision. Confirm what can continue while it is being evaluated and what needs to wait.
If the timing effect is not yet known, record the missing information and who will obtain it. Ask whether the change affects the expected completion, access to the work area or planned utility interruptions. Keep confirmed implications separate from estimates and open questions.
Separate a request for information from approval
When exploring an option, state that you are requesting information rather than approving the proposed change. Ask the project team to confirm whether any investigation, purchasing or work needs separate authorization, and document your decision before that activity proceeds.
Copy this remodel change-request record
Use a separate entry for each proposed revision. Fill unknown fields with “unresolved” and name the person responsible for the next answer. The record can accompany the project team’s paperwork rather than replace it.
- Change identifier and work area: ______. Give the request a distinct label and identify its location.
- Original scope reference: ______. Identify the agreed document, drawing, selection or earlier revision being changed.
- Requested revision: ______. Describe what is added, removed or substituted and what remains unchanged.
- Reason and supporting information: ______. Record why the change is proposed and where relevant photos, notes or specifications are saved.
- Affected selections and adjacent work: ______. Identify revised products, dimensions, connections, surfaces and details needing confirmation.
- Price adjustment and credits: ______. Record the proposed adjustment, its inclusions and exclusions, unresolved pricing and effect on the project total.
- Schedule implications: ______. Record affected activities, completion expectations and any timing still awaiting confirmation.
- Dependencies and responsibilities: ______. Identify required checks, purchasing decisions, coordination and who handles each.
- Open questions: ______. State each unanswered question, its owner and the information needed to resolve it.
- Decision and authorization scope: ______. Record the status, who needs to approve and exactly what the decision covers.
- Retained version and approval record: ______. Identify the final revision, approval details, attachments and where the shared copy is stored.
Retain the agreed version and close the loop
Before approving, read the final revision alongside its attachments. Check that the written scope, pricing status and schedule notes reflect the same proposal. If something changed during discussion, ask for the record to be updated rather than relying on a verbal qualification.
Keep the agreed version and approval record together. Mark older proposals as superseded, and confirm that people handling affected purchases or work have the current information. A later revision should identify what it changes instead of silently overwriting the earlier decision.
If you are still choosing between original proposals rather than revising an agreed scope, use the guide to comparing remodeling estimates when scopes differ. That is a separate decision from approving a later change.